Use these guides to prepare the base model, door and market data, branding, finish, packaging, app or platform requirements, samples, approvals and change records before an OEM or private-label smart lock project moves into production.

Project brief Controlled brand files Sample and golden sample Change and production release
Smart lock sample, mortise, branding files, packaging artwork and approval documents prepared for OEM review.
OEM Project Control Approve the configuration, files and revision—not only the physical sample.

A controlled project links the selected model, door data, branding, functions, documents, sample approval and production-release record.

Direct Answer

Prepare OEM Work as a Controlled Configuration

An OEM smart lock project should be prepared as a controlled configuration, not a list of customization wishes. Define the base model, door and market requirements, branding, finish, packaging, app or platform scope, approval criteria, golden sample and change-control process before production release.

Four OEM Project Signals

Separate the Inputs Before Requesting a Sample

01 Product Basis

Start with a selected product, door and market.

The base platform, mortise, door construction, target market and expected quantity determine which branding, configuration and development routes can be reviewed.

02 Controlled Files

Prepare identifiable artwork and specification inputs.

Logo files, colors, labels, manuals, packaging, function lists and platform requirements need a version, responsible owner and approval reference.

03 Approval Reference

Define exactly what the sample approval covers.

Appearance, finish, hardware, functions, software, accessories, labels, manuals, packaging and recorded deviations require separate approval evidence.

04 Change and Release

Control revisions before production starts.

Changes to model, material, finish, mortise, firmware, app, artwork or packing must be assessed, approved and released to the correct functions.

Start by OEM Project Task

Choose the Guide That Matches the Current Project Decision

Start with the issue blocking feasibility, sample approval or production release. Each route leads to the focused guide that owns the decision.

Project Brief

What must be prepared before OEM feasibility review?

Define the base product, door data, market, functions, branding, finish, packaging, platform requirements, quantity, documents and approval workflow.

Open Project Preparation Checklist
Private Label

Which brand and presentation files does the order require?

Organize the model, logo, finish, packaging, labels, manuals, app expectation and approval references before requesting a branded sample.

Open Private Label Checklist
Sample Approval

What should become the approved production reference?

Separate evaluation samples, customized samples, golden samples, linked files, deviations and first-production comparison.

Review Golden Sample Approval
MOQ and Tooling

Which customization depth is driving order quantity and development cost?

Separate standard branding and packaging from configuration changes, software scope, new parts, moulds, fixtures and engineering validation.

Review MOQ and Tooling Factors
Change Control

What changed after sample approval and who must approve it?

Track revisions to hardware, mortise, finish, firmware, app, artwork, labels, manuals and packaging before production release.

Review Change Control

Focused OEM Project Guides

Resolve the Narrow Approval or Customization Question

01 Private Label

Private Label Smart Lock Checklist

Organize the model, logo, finish, packaging, labels, manuals, platform expectation and approval records for a private-label order.

Open Private Label Checklist
02 Sample Approval

Smart Lock Golden Sample Approval Process

Define what the retained sample represents, which files remain controlling and how deviations and first-production units are reviewed.

Review Golden Sample Approval
03 MOQ and Tooling

Smart Lock MOQ and Tooling Cost Factors

Separate standard branding from configuration changes, software scope, new components, tooling, fixtures and validation requirements.

Review MOQ and Tooling Factors
04 Logo and Packaging

Smart Lock Logo and Packaging Customization Requirements

Prepare artwork, placement, color, labels, barcode, box dieline, carton marks, manual and market constraints.

Review Logo and Packaging Requirements
05 Branding Scope

Smart Lock App Branding vs Hardware Branding

Compare physical brand elements with platform, account, software, cloud and store-publication dependencies.

Compare App and Hardware Branding
06 Change Control

Smart Lock Change Control Before Mass Production

Control proposed revisions, affected files, impact review, approvals, superseded references and production release.

Review Change Control

OEM Project Files and Sample-to-Production Workflow

Move From Buyer Inputs to a Controlled Production Release

01

Define the Product Basis

Input: Buyer, brand, target market, application, door or mortise, base model direction, quantity range and required functions.

Output: Project brief, selected direction and open-question register.

Do not approve customization until the base product and physical application are defined.
02

Define and Classify the Customization

Input: Logo, finish, labels, packaging, manual, accessories, function package, app or platform and appearance or structural changes.

Output: Standard branding, configuration customization or development-review classification.

The classification starts feasibility review; it does not guarantee feasibility.
03

Control the Project Files

Input: Artwork, finish reference, labels, packaging dieline, manual source, function matrix, platform requirement, door drawing and document list.

Output: File register with version, owner, status and approval reference.

Chat messages and email attachments must not remain the only approval record.
04

Review Feasibility, Commercial Basis and Sample Plan

Input: Model compatibility, door fit, branding method, finish, packaging, platform availability, tooling, testing, documents and commercial drivers.

Output: Written feasibility response, quotation basis, exclusions, risks and sample plan.

A quotation does not replace technical approval.
05

Approve the Sample and Linked Configuration

Input: Hardware, mortise, accessories, appearance, finish, functions, platform, labels, manual, packaging, documents and deviations.

Output: Approved sample record, retained reference, approved files and deviation list.

A physical sample does not automatically approve hidden software, documents or future component substitutions.
06

Control Changes and Release Production

Input: Change request, affected item, cost or schedule impact, test or document impact, new revision, approval and effective batch.

Output: Controlled production package, first-production review and repeat-order reference.

Superseded files must not remain active, and repeat orders require review of component, software, finish, packaging and document changes.

Project Input and Approval Register

Identify the Input, Review, Approval Evidence and Owner

Input GroupBuyer InputReview FocusApproval EvidenceOwner
Product and Market Basis Buyer, brand, target market, application, door data, model direction and quantity. Product availability, physical fit, configuration route and market-document implications. Approved project brief and quotation configuration. Buyer, Commercial and Product
Brand and Appearance Files Logo artwork, finish reference, label text, barcode, manual language and packaging artwork. Method, placement, process, consistency, production and market constraints. Approved artwork, finish reference, labels, manual and packaging sample. Buyer Brand Team, Product, Packaging and Quality
Function and Platform Scope Unlock methods, accessories, automation, app or platform, local and remote functions, roles and account ownership. Selected-model availability, gateway or platform dependencies, region and commercial scope. Approved function matrix, platform note, current manual, demonstration and sample result. Buyer Product Team, Technology and Commercial
Sample and Golden Sample Sample purpose, review criteria, approvers, deviations and retained-reference requirements. Sample type, version, test coverage, file linkage and what the physical sample cannot represent. Approval record, Golden Sample ID, linked files and deviation list. Buyer Approver, Project Owner, Quality and Production
Tooling and Commercial Development Requested new part, expected volume, ownership requirement, target timing and change expectations. Tool type, engineering scope, cost, schedule, maintenance, reuse and design-change impact. Tooling agreement, approved drawing and commercial approval. Engineering, Commercial and Buyer
Change and Production Release Requested revision, reason, required date, affected item and order or batch. Feasibility, cost, schedule, testing, documents, inventory and production impact. Approved change record, effective revision, handover package and release record. Project Owner, Commercial, Engineering, Quality and Production
Input RequiredMissing input has an owner and approval gate. Under ReviewCommercial, product, engineering or quality review is active. ApprovedThe current version can control the next step. Approved With ConditionsApproval is limited by recorded deviations or assumptions. ReviseThe input must be corrected before release. SupersededA newer approved version replaces this reference. ReleasedThe controlled package is handed to production.

ISO 10007:2017 is used here as configuration-management guidance, not as a SivoLock project certification claim. ISO 9001 documented information concepts support file, version and approval records, not unproved SivoLock certification scope.

Approved smart lock drawings, artwork, function matrix and revision records prepared for production handover.

OEM/ODM FAQ

Questions Before OEM Sample or Production Approval

What is the difference between this Resource Hub and the SivoLock OEM/ODM page?

This Resource Hub teaches buyers how to prepare project inputs, files, samples, approvals and change records. The SivoLock OEM/ODM page presents SivoLock’s commercial customization routes and inquiry process. The OEM/ODM Capabilities page provides development and production evidence.

What should a buyer prepare before requesting an OEM smart lock quotation?

Prepare the target market, application, door and mortise data, base product direction, quantity, functions, branding, finish, packaging, manuals, labels, platform requirements, document expectations, sample purpose and approval responsibilities. Record unresolved items with assumptions and owners rather than leaving blank fields.

Is a private-label smart lock project only a logo change?

Not necessarily. Some projects involve only approved logos, labels, manuals or packaging. Others involve finish, mortise, accessories, functions or platform requirements. Each request depends on the selected product, quantity, feasibility and target market.

Does an approved sample automatically become the golden sample?

Only when the project identifies what the sample represents, assigns an ID and links it to approved drawings, functions, software or platform notes, artwork, labels, manuals, packaging and deviations. A physical sample alone cannot control every hidden or document-based requirement.

Are MOQ and tooling costs the same for every OEM project?

No. They can vary by base product, quantity, finish, packaging, branding method, software scope, new components, moulds, fixtures, testing, documents and engineering risk. Compare the same customization depth before comparing MOQ or development cost.

Can hardware branding and app branding be approved together?

They can be part of one project, but they are different scopes. Hardware branding may involve the panel, labels, manuals and packaging. App branding can depend on the selected product, current platform, region, account structure, software version, store publication, cloud and other technical or commercial dependencies.

What changes should be controlled before mass production?

Control changes to the base product, mortise, components, material, finish, function package, firmware, app or platform, logo, labels, manuals, packaging and included accessories. Review cost, schedule, testing, documents, inventory and previous approvals before releasing a new revision.

Can the same golden sample be used for repeat orders?

It can remain an important reference, but repeat orders should still review component, firmware or platform, finish, artwork, packaging, document and supplier changes. Link every approved deviation or new revision to the retained reference.

Where should a multi-door OEM project prepare quantities and model mapping?

Use Project & RFQ Guides for Door Schedules, opening IDs, quantities, model mapping, approvals, spares and delivery phases. OEM/ODM Guides control customization inputs and sample-to-production records.

Ready for OEM Project Review?

Send a controlled project brief before requesting production approval.

Share the product direction, door and market data, quantity, functions, branding, finish, packaging, app or platform needs, required documents, sample purpose, approvers and open questions so SivoLock can review the appropriate commercial and technical route.

  • Buyer, brand and target market
  • Application, door and mortise data
  • Base product or model direction
  • Quantity and requested schedule
  • Required functions and accessories
  • Logo, finish, labels and packaging
  • Manual and language requirements
  • App or platform requirements
  • Reports and target-market documents
  • Sample purpose and approval criteria
  • Golden Sample and retained references
  • Change-control and production-release owner