Plan smart lock spares by door group; a percentage of the order hides which doors the spares fit. For each group of identical doors, decide how a failed door is restored (a complete lock exchange, a module or a fitting kit), who does it, where the part is kept and how long a replacement takes to arrive. The quantity that counts is compatible, serviceable stock in the right place; boxes awaiting inspection, parts reserved for another job and items still in transit count later.
The plan needs the installed configurations, the effect of a failure, the replacement procedure, the replenishment time and the storage conditions. A small group of critical doors can justify local stock even when its parts are rarely used.
The worked examples below cover a 120-door, two-site stock plan and a reorder calculation.
Start with recovery, not a spare percentage
Start with what happens when a door stops working. The fix can be configuration, adjustment, a replacement component or a complete lock exchange. Stock the items for the fixes your team can carry out.
A spare earns its shelf space when it is compatible, complete and can be fitted by someone on hand with the manufacturer's procedure. A cheap internal part that needs specialist tools and off-site work helps little; a complete assembly costs more but can be swapped quickly.
Set the recovery target per type of door. A staffed internal door with another way in needs less than a remote property entrance. Include travel, site access and configuration time as well as the time to get the part.
A box on the shelf removes the wait for the part. Diagnosis, access, fitting and a function check still take their own time.
Map the installed base into compatible groups
Build the plan from the installed door and hardware records. For each group, record what decides whether a replacement fits: hardware revision, dimensions, handing, power, connectors and any electronic or software dependency.
Group items only when they are known to be interchangeable for the job. Similar looks, the same product family or matching faceplates do not prove the fit, and some replacements also need an adapter, a matching part or a configuration step. Our A2 IP66 waterproof smart lock, for example, takes four different mortises (6068, 4585, Russian 6585, Russian 6085), so a spare A2 is stocked per mortise, and its Local, Tuya and TTLock versions are separate spares again.
The UFGS door-hardware guide specification organizes hardware around identified items and openings, linking components, quantities and opening descriptions in one schedule. Source: UFGS 08 71 00, Hardware Schedule
Count installed units and openings separately: a paired opening can hold several items, and one shared gateway serves several openings.
Include retained equipment the team maintains, and drop retired equipment that is still listed in an old schedule. Whether a lock is serviced by module or as a whole comes from its architecture; see integrated and modular lock architecture.
Choose parts the service team can use
Split the list into consumables, replaceable components, complete assemblies and shared-system equipment; each is restocked differently.
| Spare category | Reason to hold it | Compatibility or recovery check |
|---|---|---|
| Specified batteries or approved power packs | Planned service and power-related recovery | Correct chemistry or pack, condition, storage and charging instructions |
| Manufacturer-approved fitting kits | Replace missing or damaged service fittings | Correct dimensions, thread, length and application |
| Approved mechanical replacement components | Restore a diagnosed mechanical function | Matching interfaces, handing and the manufacturer's replacement procedure |
| Approved electronic modules | Restore a diagnosed electronic function | Hardware revision, connector, firmware and configuration dependencies |
| Complete lock assemblies or kits | Support an approved assembly exchange | Complete opening fit, required accessories and commissioning procedure |
| Shared communication or power equipment | Restore a shared function across many doors | Architecture, provisioning, entitlement and affected openings |
Only some categories need stock. Some locks are serviced only as complete assemblies; some parts go back to the manufacturer instead of being opened on site. The service model decides what goes on the shelf.
Keep fittings in their labeled service kits. A screw of the wrong length or thread can look right and still be wrong.
List what each complete kit includes. A lock arriving without its mortise, cable, adapter or mounting hardware leaves the door shut, and accessories already in the kit need buying only once.
Prioritize failure consequences and recovery time
Prioritize the items whose absence would stop a door being restored in time. Weigh the function lost, the number of doors affected, any workaround and how long a technician takes to arrive.
A shared component matters because one fault can hit management functions on many doors. On our TTLock versions a failed gateway stops remote changes, while fingerprints, PINs and cards already enrolled keep working within their validity. Stock for that effect.
A rarely used part can still need stock when it takes long to replace and has no substitute. A part that is easy to get, where a short wait is acceptable, needs little.
If everything is top priority, nothing is. Give each item a one-line reason: local recovery, long lead time, frequent use, shared impact or an acceptable wait.
On fire-rated, egress and other regulated doors, a replacement must meet the same product and opening requirements as the original. The fire door, egress and accessibility guide provides the broader review context.
Estimate demand from parts consumed
Count parts used; complaints, tickets and visits overstate it. Several tickets can be one incident, one incident can use two parts, and an adjustment uses none.
Keep installation losses and early defects separate from normal operating demand, or a rough commissioning period inflates the long-term forecast. Planned upgrades and battery rounds get their own quantities.
Forecast from the locks that actually use the part: a component in 30 of 120 locks is forecast from 30. When the installed base changes, update the forecast.
For a new project with no history, set recovery stock by choice and write down the assumptions instead of inventing a failure rate.
Rare demand also arrives in clusters. One unit every two months on average can mean three in one week after a common installation problem or batch issue.
Measure the full replenishment time
Replenishment time runs until the part is ready for use on site: ordering approval, processing, production or picking, transport, import, receiving inspection and any configuration.
So the dispatch date is only part of it. Find out whether the item is stocked, made to order or comes from a repair return, and record the normal time and the delays that would change your plan.
SAP's planning material counts purchasing, delivery and goods-receipt processing in replenishment lead time, and uses safety stock to cover extra consumption and late deliveries. Source: SAP, Using Forecast in Reorder Point Planning
Repair returns need their own timing: a unit sent away counts as incoming only once its return date is known. A warranty replacement can still arrive too late for an urgent repair.
Set a reorder rule that matches the review process
A simple starting relationship is:
Reorder point = expected consumption during replenishment lead time + an explicit buffer.
With an average demand rate, the lead-time portion is average units per week multiplied by replenishment weeks. SAP presents the same basic relationship using daily requirements and lead time. Source: SAP reorder-point planning
Give the buffer a reason: uncertain demand, variable lead time or an extra recovery need. One extra unit by judgment is a clear starting rule; a stated service level such as 95% needs a statistical model and data behind it.
Decide when stock is reviewed. A continuously watched rule orders when stock hits the trigger; a team that reviews every two weeks must also cover the time until the next review.
For a periodic review, the target covers expected demand over the review interval plus the replenishment time, plus the buffer. Keep the two policies separate: each has its own target and ordering rule.
Separate the trigger from the order quantity
The reorder point says when to order; the order quantity says how many. The quantity can top stock up to a target, follow an economic batch or match a pack size; say which.
If the calculation says two but parts come in packs of five, the order is five, and the extra three are stock to plan for.
For rarely used but important items, a fixed minimum replaced after each use is often clearer than a formula. It still needs a replenishment time and a plan for when the minimum cannot be restored quickly.
Distinguish immediate stock from inventory position
Immediate availability is serviceable stock in the right place, after reservations. Incoming orders count for purchasing, but they cannot restore a door today.
For the examples in this guide, use:
Inventory position = uncommitted serviceable stock + firm replenishment orders − unfilled demand not already reserved.
Count each unit or job once: a job is either reserved or unfilled, never both. Leave quarantined items out, and check the arrival dates of incoming orders.
The position can look fine while a site is short. If the remaining kits are all at the other site, or the incoming stock lands after the repair date, the door still waits. Check availability per site as well as the company total.
Worked spare plan: 120 doors across two sites
Take a project with two confirmed, non-interchangeable lock configurations, Group A and Group B.
Site 1 has 60 Group A doors and 20 Group B doors. Site 2 has 20 Group A doors and 20 Group B doors. The installed total is therefore 80 Group A and 40 Group B openings, or 120 doors. Each opening has one lock.
Both sites have trained staff for a complete-kit exchange and its configuration. Module replacement goes through a central technician. Stock can move between sites within an agreed window, but each site needs its own first response.
The quantities are chosen holdings. Prices are example figures in USD, excluding taxes, storage, labor and freight. Batteries and shared infrastructure spares are planned separately.
| Item | Quantity | Assumed unit price | Initial stock cost | Location |
|---|---|---|---|---|
| Complete Group A replacement kit | 4 | $150 | $600 | Three at Site 1; one at Site 2 |
| Complete Group B replacement kit | 2 | $180 | $360 | One at each site |
| Approved Group A service module | 2 | $40 | $80 | Central technician stock |
| Approved Group B service module | 1 | $50 | $50 | Central technician stock |
| Approved fitting service kit | 6 | $8 | $48 | Three at each site |
| Total | 15 stock units across five item lines | — | $1,138 | Distributed as stated |
The fitting kits suit both groups for their task; the lock kits and modules do not cross between A and B. Complete kits already include their fittings, and the separate fitting kits are for other service work.
Six complete spare locks for 120 doors works out at 5%. That number came out of this plan; a project with more configurations, slower supply or other priorities would land somewhere else.
The central modules are a separate recovery route from the local kits. When a kit replaces a lock, the removed lock can go into repair, so issuing a kit does not mean reordering modules.
Worked reorder example for Group A kits
Assume the planning demand for Group A complete kits is 0.5 units per week and normal replenishment takes four weeks from ordering to accepted usable stock. The expected lead-time demand is two units. The team selects a one-unit buffer, giving a reorder point of three units.
Under this continuously reviewed policy, the team orders when inventory position is at or below three and tops it up to a chosen target of five.
Now consider this stock status:
| Status | Quantity | Treatment |
|---|---|---|
| Physical Group A kits present | 4 | Includes one quarantined item |
| Quarantined kit | 1 | Excluded from serviceable stock |
| Serviceable kits | 3 | Available before reservations |
| Kit reserved for a specific scheduled job | 1 | Not available for another job |
| Uncommitted serviceable kits | 2 | Immediate unallocated stock |
| Firm incoming replenishment | 2 | Counts for purchasing position; not available today |
| Unfilled demand with no reservation | 1 | Subtracted once from inventory position |
The inventory position is 2 + 2 − 1 = 3 units. The stated policy triggers a purchase of 5 − 3 = 2 units, assuming no minimum-order constraint. After placing that order, inventory position becomes five; immediate uncommitted stock is still two until stock is issued or received.
If the unfilled job is at the same site, it uses one of those two units, leaving one free kit on the shelf and the reserved kit committed. Check the dates of use and receipt against each other as well as the total.
What if lead time doubles?
At eight weeks, the same mean demand implies four units during replenishment. Retaining the explicitly chosen one-unit buffer produces a trigger of five. If the team keeps the same two-unit gap between trigger and target, the target becomes seven.
Delays or demand clusters can still exceed that. Compare it with a shorter supply route, a different repair arrangement or more local stock before choosing.
What if stock is reviewed periodically?
Under a separate two-week review policy with four-week replenishment, the simple protection period is six weeks. At 0.5 units weekly, expected consumption is three units; adding a one-unit buffer gives a four-unit planning target before considering other scheduled requirements.
This four-unit target belongs to the periodic-review policy; the five-unit target and trigger belong to the continuous one.
Decide where stock should be kept
Central stock shares parts across sites and avoids duplicate holdings. Local stock shortens the response where travel or access windows matter. Most multi-site projects end up with a mix, split by the recovery target.
Test the transfer: who releases the part, how it gets to site and whether a technician can attend. A central store closed after office hours cannot meet an evening repair target.
Record both sides of every transfer and recheck the sending site's cover, or two sites will count the same kit.
Report stock by compatible group and site. A combined count across revisions can show a surplus while one installed group has no usable spare.
Keep hardware and software compatibility together
A replacement board, reader, gateway or connected lock may need the right firmware, account link, credentials or configuration before it is ready, even straight from a sealed box.
NISTIR 8259A lists device identification, authorized configuration, data protection and software updates among IoT capabilities. For spares, that means keeping the device identity and configuration path when connected equipment is replaced. Source: NISTIR 8259A
Keep a short compatibility record: the part number, the installed versions it serves, companion items, setup steps and how the match was confirmed. A superseding part number gets checked before it is treated as a direct substitute.
Equipment used elsewhere before must be removed from the old account and reset through the supported process. Keep credentials off inventory labels and store recovery information under the project's access controls.
A replacement is finished when its functions work at the door and in the connected system, and the asset record is updated; a bench test is only the first step.
Store, issue and return parts without losing readiness
Keep the label with the item. The UFGS hardware specification calls for individual containers with their fittings, instructions and labels tied to the hardware schedule, which is a good rule for service kits too. Source: UFGS 08 71 00, Delivery, Storage and Handling
Follow each item's storage and handling instructions: batteries, electronic modules and mechanical assemblies differ. Keep the protective packaging, follow the electrostatic-handling instructions, and take battery storage life and recharge intervals from each pack's own instructions.
Use clear stock states: received but unchecked, serviceable, reserved, issued, quarantined, under repair and retired. A returned part goes back to serviceable only after a recorded check or repair.
Issue parts against an opening or job, and record what was removed, what was fitted and where the removed item went. A replacement and its later repair then do not show up as two unexplained losses.
Check usability as well as quantity at each review. Missing fittings, outdated compatibility records or a damaged pack reduce what the team can deploy without changing the box count.
Plan replenishment and obsolescence together
Stock goes stale when installed configurations change, software support ends or the service arrangement changes. Review open purchase orders whenever a fleet change is approved.
Keep a record of replacement part numbers, supported revisions, order quantities, lead times and discontinuation notices. A last-time buy follows the remaining installed locks, the remaining support period and realistic consumption; the original spare percentage is no guide.
Keep stock for retired equipment separate from active spares, and decide whether to return, redeploy or dispose of it.
For budgeting, a spare is a cost when it is bought; fitting it later costs labor only, while restocking the shelf is a new purchase. Storage, configuration and fitting are separate costs. The smart lock total cost of ownership guide explains how to connect these amounts to the wider project model.
Order spares by door group
A spare-parts order works best when it follows the installed configurations instead of a general accessories list: each item, the door group it serves, the work needed to fit it, and what each package contains. Add the stock location, ordering trigger, review interval and replenishment time, with a reason for any unusual holding, such as a critical remote door or a part with no short-term substitute.
Frequently asked questions
What percentage of smart locks should a project keep as spares?
Work it out per door group rather than starting from a percentage: the number of identical doors, how fast a failed door must be restored, how long a replacement takes to arrive and who can fit it. In the 120-door example in this guide that comes to 5% complete spare locks, plus modules and fitting kits.
Can one spare cover different models or revisions?
Only when it is known to fit and work for that job: check the mechanical interfaces, power, connectors, software and companion parts. A similar look or the same product family settles none of them.
Do incoming orders count as available stock?
For purchasing decisions, yes; for an urgent repair, no. Check when and where they arrive, because a late delivery does not fix today's shortage.
How should failed parts awaiting warranty service be counted?
Outside serviceable stock, with the claim tracked separately. They count as incoming once the replacement or repaired item has a confirmed delivery date.
References
- SAP Learning. Using Forecast in Reorder Point Planning. The relationship between demand, replenishment lead time and safety stock.